Case story

  • Georgia

Parties

CAO Case - Georgia / BTC Pipeline-14 / Vale

Georgian Young Lawyers Association Complaint Regarding BTC Pipeline, Vale, Georgia 2004

This case story originates from BASESwiki.org, a platform based on wiki style contributions from a virtual network or individuals, companies and organizations with relevant expertise. Though some of the information may be outdated or inaccurate due to the wiki-nature of the BASESwiki platform, they still present a valuable resource. ACCESS is reviewing and updating all BASESwiki case stories. 

Story

The Baku-Tbilisi-Ceyhan (BTC) oil and gas pipeline is a 1,768 km long crude oil pipeline stretching from the Caspian Sea to the Mediterranean Sea. It is the second longest oil pipeline in the world and passes through Azerbaijan, Georgia and Turkey. IFC has invested $250 million since 2003 and the total project cost is approximately $3.6 billion. The project is operated by BTC Co., which comprises a consortium of 11 partners. To date, CAO has received 33 complaints in relation to the project ranging from individuals to communities to local organizations. On August 8, 2004, the CAO received three separate complaints from individual residents of the village of Vale regarding land compensation. The complaints were filed by the Georgian Young Lawyers Association (GYLA) on behalf of the residents.

CAO Action

The CAO accepted the complaints on December 8, 2004. CAO worked together to facilitate agreements between BTC Co. and GYLA to resolve the complaints.

Outcome

Case Status: Closed

BTC Co. and GYLA negotiated and reached settlement on the three claims, and CAO closed the complaints in December 2005.

References

CAO case story page: http://www.cao-ombudsman.org/cases/case_detail.aspx?id=57

Contributor(s): This article was modified by Nicolaclayre (4), Pic1 (1), and Kyle (1).